Sunday 27 October 2013

Ho Hum

Scaffolding has come down now and roof tiles on lower part have been laid but not finished.

Thursday 17 October 2013

Still moving along slowly

Eaves erected and painted this week. Top floor bricks cleaned

Saturday 12 October 2013

Moving along slowly

Bricks have finally been completed. This last week we had facias and gutters installed and the top level roof tiles laid. Still a long way to go to finish the outside. Still need eaves done and bricks cleaned.