Back from holidays. Most of the house is complete. The only thing left is door handles, cleanup and carpet as far as I can see. SS told us that carpet is due 9 Feb and PCI some time after that. Expected move in date is end Feb.
Driveway was done before Christmas and so has had plenty of time to dry.
BuildingWisdomWashington 29
Wednesday, 22 January 2014
Sunday, 1 December 2013
We have stalled again
SS rang to say that our tiling was supposed to start this week - 2 Dec - but the tiles haven't arrived from overseas. This is strange considering we selected from the standard builder's range month's ago. This means we have to wait another week before tiling can begin. We still don't have a garage door either. I guess that means nothing will happen this week.
Tuesday, 26 November 2013
Lots happening but not enough to move in before Christmas
We have been away and have come back to quite a bit of work done. We now have lockup. Internal walls/ceilings are finished and are ready to start painting. Wet areas are being done and kitchen being installed. This means the house will be just about finished before Christmas and then we will need to wait until end January for them to start again. Can't imagine what else would need to be done after that, other than the carpet and driveway.
This means another month of paying almost full mortgage and rent. Not easy, especially around Christmas. I guess we can pack and organise over the Christmas break ready for moving. Whoopy.
Have an inspection next week with the SS. We haven't been inside during the build because any time we have been there, no one else has, so I hope we don't find any major problems. Will post pictures after that.
This means another month of paying almost full mortgage and rent. Not easy, especially around Christmas. I guess we can pack and organise over the Christmas break ready for moving. Whoopy.
Have an inspection next week with the SS. We haven't been inside during the build because any time we have been there, no one else has, so I hope we don't find any major problems. Will post pictures after that.
Friday, 8 November 2013
Another slow week
Went out to the site today, gate was wide open, and no one there, as usual. Was told last week that gyprock would be completed this week, but nothing has started.
The brickwork has been cleaned on the lower part of the house but the fence is still filthy on both sides. I don't know how they could make such a mess.
The gyprock is in the garage, but has been most of the week, so if it rains, it will get all wet, as the garage faces west.
The brickwork has been cleaned on the lower part of the house but the fence is still filthy on both sides. I don't know how they could make such a mess.
The gyprock is in the garage, but has been most of the week, so if it rains, it will get all wet, as the garage faces west.
Sunday, 3 November 2013
We're moving along again
Last week we had the lower roof tiles finished, stria board erected, electricals completed and aircon ducting installed. This week SHOULD see the linings started. If I can work out how to load some pictures, I will do that shortly.
Sunday, 27 October 2013
Ho Hum
Scaffolding has come down now and roof tiles on lower part have been laid but not finished.
Thursday, 17 October 2013
Still moving along slowly
Eaves erected and painted this week. Top floor bricks cleaned