Saturday, 12 October 2013
Moving along slowly
Bricks have finally been completed. This last week we had facias and gutters installed and the top level roof tiles laid. Still a long way to go to finish the outside. Still need eaves done and bricks cleaned.
Sunday, 22 September 2013
Where we are at
Well we were off to a good start.
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July - Blocked scrapped
12 August - Slab poured
21 August - Drainage completed
26 August - Frames started
2 September - Frames completed
10 September - Plumbing completed
13 September -Brickwork completed lower floor
16 September - Scaffolding erected for second floor
Week 16 - 22 September - NOTHING happened bricks were supposed to be completed - NOT HAPPY
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July - Blocked scrapped
12 August - Slab poured
21 August - Drainage completed
26 August - Frames started
2 September - Frames completed
10 September - Plumbing completed
13 September -Brickwork completed lower floor
16 September - Scaffolding erected for second floor
Week 16 - 22 September - NOTHING happened bricks were supposed to be completed - NOT HAPPY
Saturday, 1 June 2013
Colour selection
Kitchen
Benchtops - Caesarstone - White Shimmer 20 mm, 40 mm for island with waterfall
Cupboards - White Gloss polyurethane, sharkedge profile
Undermount sink
Tiles - Bathroom, Ensuite, Toilet and Powder room
Walls - White Gloss 250 x 400 mm
Floors - Grey 300 x 300
Front porch - Cream Grip
Bathrooms
Benchtops - Caesarstone - White Shimmer 20 mm
Cupboards - Expresso Natural laminate, drawers included
Wall colours
Crisp White
Floors
Carpet - Godfrey Hirst - Cobbler - upstairs
Downstairs - Laminate Flooring - to be installed by owner
External - Facade - Classic
Bricks - PGH Chocolatto with ironed off white motar
Windows - Anodic Natural Matt
Roof - Bristile Prestige - Titanium
Fascia - Dune
Gutter - Monument
Barge - Dune
Garage door - Panel lift profile -contemporary - classic cedar
Driveway - Barley - brushed
Front door - clear finish gloss
Cladding - Dune
Downpipes - Monument
Extras
Doorbell
Data points
Privacy adaptors to bathrooms
Extra controller for aircon upstairs
Benchtops - Caesarstone - White Shimmer 20 mm, 40 mm for island with waterfall
Cupboards - White Gloss polyurethane, sharkedge profile
Undermount sink
Tiles - Bathroom, Ensuite, Toilet and Powder room
Walls - White Gloss 250 x 400 mm
Floors - Grey 300 x 300
Front porch - Cream Grip
Bathrooms
Benchtops - Caesarstone - White Shimmer 20 mm
Cupboards - Expresso Natural laminate, drawers included
Wall colours
Crisp White
Floors
Carpet - Godfrey Hirst - Cobbler - upstairs
Downstairs - Laminate Flooring - to be installed by owner
External - Facade - Classic
Bricks - PGH Chocolatto with ironed off white motar
Windows - Anodic Natural Matt
Roof - Bristile Prestige - Titanium
Fascia - Dune
Gutter - Monument
Barge - Dune
Garage door - Panel lift profile -contemporary - classic cedar
Driveway - Barley - brushed
Front door - clear finish gloss
Cladding - Dune
Downpipes - Monument
Extras
Doorbell
Data points
Privacy adaptors to bathrooms
Extra controller for aircon upstairs
Building Wisdom Homes Washington 29 at Gregory Hills
Building a double storey, Washington 29 at Gregory Hills. Found other building blogs very useful, so decided to add to the information. Hope you find it useful.