Saturday, 12 October 2013

Moving along slowly

Bricks have finally been completed. This last week we had facias and gutters installed and the top level roof tiles laid. Still a long way to go to finish the outside. Still need eaves done and bricks cleaned.

Sunday, 22 September 2013

Where we are at

Well we were off to a good start.
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July - Blocked scrapped
12 August - Slab poured
21 August - Drainage completed
26 August - Frames started
2 September - Frames completed
10 September - Plumbing completed
13 September -Brickwork completed lower floor
16 September - Scaffolding erected for second floor
Week 16 - 22 September - NOTHING happened bricks were supposed to be completed - NOT HAPPY

Saturday, 1 June 2013

Colour selection

Kitchen
Benchtops - Caesarstone - White Shimmer 20 mm, 40 mm for island with waterfall
Cupboards - White Gloss polyurethane, sharkedge profile
Undermount sink

Tiles - Bathroom, Ensuite, Toilet and Powder room
Walls - White Gloss 250 x 400 mm
Floors - Grey 300 x 300
Front porch - Cream Grip

Bathrooms
Benchtops - Caesarstone - White Shimmer 20 mm
Cupboards - Expresso Natural laminate, drawers included

Wall colours
Crisp White

Floors
Carpet - Godfrey Hirst  - Cobbler - upstairs
Downstairs - Laminate Flooring - to be installed by owner

External - Facade - Classic
Bricks - PGH Chocolatto with ironed off white motar
Windows - Anodic Natural Matt
Roof - Bristile Prestige - Titanium
Fascia - Dune
Gutter - Monument
Barge - Dune
Garage door - Panel lift profile -contemporary - classic cedar
Driveway - Barley - brushed
Front door - clear finish gloss
Cladding - Dune
Downpipes - Monument

Extras
Doorbell
Data points
Privacy adaptors to bathrooms
Extra controller for aircon upstairs





Building Wisdom Homes Washington 29 at Gregory Hills

Building a double storey, Washington 29 at Gregory Hills.  Found other building blogs very useful, so decided to add to the information.  Hope you find it useful.