We have been away and have come back to quite a bit of work done. We now have lockup. Internal walls/ceilings are finished and are ready to start painting. Wet areas are being done and kitchen being installed. This means the house will be just about finished before Christmas and then we will need to wait until end January for them to start again. Can't imagine what else would need to be done after that, other than the carpet and driveway.
This means another month of paying almost full mortgage and rent. Not easy, especially around Christmas. I guess we can pack and organise over the Christmas break ready for moving. Whoopy.
Have an inspection next week with the SS. We haven't been inside during the build because any time we have been there, no one else has, so I hope we don't find any major problems. Will post pictures after that.
Tuesday, 26 November 2013
Friday, 8 November 2013
Another slow week
Went out to the site today, gate was wide open, and no one there, as usual. Was told last week that gyprock would be completed this week, but nothing has started.
The brickwork has been cleaned on the lower part of the house but the fence is still filthy on both sides. I don't know how they could make such a mess.
The gyprock is in the garage, but has been most of the week, so if it rains, it will get all wet, as the garage faces west.
The brickwork has been cleaned on the lower part of the house but the fence is still filthy on both sides. I don't know how they could make such a mess.
The gyprock is in the garage, but has been most of the week, so if it rains, it will get all wet, as the garage faces west.
Sunday, 3 November 2013
We're moving along again
Last week we had the lower roof tiles finished, stria board erected, electricals completed and aircon ducting installed. This week SHOULD see the linings started. If I can work out how to load some pictures, I will do that shortly.
Sunday, 27 October 2013
Ho Hum
Scaffolding has come down now and roof tiles on lower part have been laid but not finished.
Thursday, 17 October 2013
Still moving along slowly
Eaves erected and painted this week. Top floor bricks cleaned
Saturday, 12 October 2013
Moving along slowly
Bricks have finally been completed. This last week we had facias and gutters installed and the top level roof tiles laid. Still a long way to go to finish the outside. Still need eaves done and bricks cleaned.
Sunday, 22 September 2013
Where we are at
Well we were off to a good start.
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July - Blocked scrapped
12 August - Slab poured
21 August - Drainage completed
26 August - Frames started
2 September - Frames completed
10 September - Plumbing completed
13 September -Brickwork completed lower floor
16 September - Scaffolding erected for second floor
Week 16 - 22 September - NOTHING happened bricks were supposed to be completed - NOT HAPPY
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July - Blocked scrapped
12 August - Slab poured
21 August - Drainage completed
26 August - Frames started
2 September - Frames completed
10 September - Plumbing completed
13 September -Brickwork completed lower floor
16 September - Scaffolding erected for second floor
Week 16 - 22 September - NOTHING happened bricks were supposed to be completed - NOT HAPPY