Well we were off to a good start.
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July -  Blocked scrapped
12 August -  Slab poured
21 August -  Drainage completed 
26 August -    Frames started 
2 September - Frames completed 
10 September - Plumbing completed 
13 September  -Brickwork completed lower floor 
16 September - Scaffolding erected for second floor 
Week 16 - 22 September - NOTHING happened  bricks were supposed to be completed - NOT HAPPY   